1. DTOS_Planning
- Technical Feasibility Study
- Proposal consulting and confirmation (Est. SPEC, Cost & milestone)
- NRE Quotaiton
2. Development:design phase (Est. 6 weeks / 2weeks circuit + 4 weeks layout)
- Experience engineer to support
- Schematic/Layout Generation
- EMC/EMI board & system advise
- Customize BIOS coding
3.Design Validation: Est. 6 weeks
- Module + Carrier Board validation
- Design Validation Tests
- MTBF prediction
- Vibration, drop and shock test
- Temperature and humidity test
- Accelerated life
- Voltage margining test
- Thermal analysis and test
- Performance test
- Compatibility test
- Customer requested test
4. Integration: Est. 4 weeks
- Embedded OS & SW customization
- Thermal solution customization
- Module & Peripheral assembly (ex: Thermal module, memory, display & HDD + OS pre-install)
5.Manufacturing or Mass Production: Est. 4 weeks
- Volume Production
- Module + Carrier board Fabrication & Assembly
- Dedicated Test Fixture Development
6. End of Life Management: Est. 4 weeks
- Component EOL Notice
- Replacement part verification
- Revision Control